Flying Eagle

 

The story of the Flying Eagle began in the beginning of 2015. Flying Eagle is a major investment project of Kotkamills at Kotka site. Our Project Director tells you more about the start and the milestones towards Consumer Boards business and the construction of the new board machine.  Step into the project!

 

25.7.2016  Stefan Fors 


The Eagle is flying

On 22 of July 2016 at 15.05 pm BM 2 was successfully in production. After very intense last two weeks of testings, all areas were ready for board production. It was for sure a very happy moment to all of us.

Read more

 


 

21.06.2016  Stefan Fors
 

Beginning of the end of the project

Mechanical installations are soon finished and almost daily we have installation inspections. Construction works are also mostly done. This can be noted in our manpower, which has now decreased to 950 from the peak week's above 1200.

Read more

 


 

04.05.2016  Stefan Fors
 

Hectic moments

We are now living probably the most hectic moments of the project. Site manpower is more than 1100 and we have have given safety trainings to more than 2600 people.
 

Read more


 

07.04.2016  Stefan Fors
 

Installations

After a period of fine tuning of the dismantling and a lot of construction activities, the mechanical installations are increasing. Also pipes, automation and electrical installations have started.

Read more

 


 

02.03.2016  Stefan Fors
 

Dismantling

The paper machine is gone. Two weeks after shut down the main machinery had disappeared and left was only a long black hole.

Read more

 


 

02.02.2016  Stefan Fors

Action

PM 2 has stopped for the last time. Early in the morning of 23.1.2016 we produced the last machine reel of Solaris® printing paper. It was of course a sentimental moment to many people at the mill. However, the new board machine will for sure fill up the empty spaces both in the soul as well as in the machine hall.

Read more

 


 

05.01.2016  Stefan Fors

The final countdown

Even the project had a short break during Christmas. But now we are back again excitingly waiting for end of January when the next step will be achieved, the final shutdown of PM2.

Read more

 


 

07.12.2015  Stefan Fors

Keeping in the schedule

The Flying Eagle is heading for the runway. At the beginning of December the project organisation will move into temporarily project facilities at the mill. Excavation work for new foundations is already proceeding, even inside the production building. Sections of both machine floor and bottom floor have disappeared, and all this while PM 2 is still producing paper at top efficiency.

Read more


 


03.11.2015 Stefan Fors
 

BM2 - new board machine
 

Here is a quite big investment project on-going at Kotkamills, and I was asked to start to write a regular blog in order to share some information how things are proceeding. Why not, I thought, writing is quite fun.

Read more


 

 